To ask the Secretary of State for Defence, what the whole life costs forecast is for AJAX.

Answered on

21 December 2021

The forecast cost for the Assessment and Demonstration & Manufacture phases and for contracted support (up to the end of the initial support contract) for the AJAX project is £5,915 million. (This forecast figure which is reviewed bi-annually will differ from the budget figure. It relates specifically to the Ajax Project within the Armoured Cavalry Programme.)


Original Source

https://questions-statements.parliament.uk/written-questions/detail/2021-12-13/91857


 